Construction began this week on the Scott Street bus detour, part of the ongoing Stage 2 LRT project. Making these changes along Scott Street will allow OC Transpo to operate its buses while crews are constructing the LRT in the Transitway trench.
To that end, our office is holding a public webinar on July 27at 7pm so you can learn what to expect during the construction of the detour and beyond.
When: Jul 27, 2021 07:00 PM Eastern Time (US and Canada)
Topic: Scott Street Detour Construction Webinar
Please click the link below to join the webinar:
https://us02web.zoom.us/j/82343435103
Passcode: 938495
Understanding that you may have several questions about the schedule before this meeting is held, our LRT Stakeholder Relations team has put together this schedule of what to expect in the coming months.
July 5th and 6th |
South side bulb-out removals |
July 7th |
Temporary paving Traffic shift to south side of right-of-way |
July 21st to August 4th |
Asphalt removals |
July 22nd to August 5th |
Granular placement + sub drains |
August 6th to 16th |
Install temporary bus platforms |
August 6th to 26th |
Concrete flatworks |
August 17th to 20th |
Pave curb strip |
August 23rd to 27th
|
Pave cycle track |
August 30th to September 20th
|
Landscaping |
July 8th to July 14th North side |
Asphalt removal Granular placement |
July 15th North side |
Asphalt widening Temporary shift to north side of right-of-way |
July 15th to August 26th |
Westboro Station civil works |
July 16th to July 23rd South side |
Catch basin relocation |
July 26th to July 28th South side |
Hydrant relocations |
July 7th to 27th North side |
Traffic plant relocation |
July 16th to 27th North side |
Asphalt removal Granular placement + sub drain |
July 19th North side |
Catch basin relocations |
July 28th to August 11th North side |
Concrete flatworks |
August 12th to 13th North side |
Pave widening |
August 16th North side |
Traffic shift |
August 16th to 25th North side |
Landscaping |
August 17th to 19th South side |
Storm line install |
August 20th to 23rd South side |
Catch basin relocation |
July 13th to August 3rd North side |
Traffic plant relocation |
July 28th to August 3rd North side |
Asphalt removals |
July 29th to August 4th North side |
Granular placement + sub drain |
August 5th to 11th North side |
Catch basin relocations |
August 12th to 23rd North side |
Concrete flatworks |
August 24th to 26th |
Pave widening on north side |
August 27th to September 3rd
|
Landscaping (north side) Asphalt removals (south side) |
August 31st to September 22nd South side |
Traffic plant relocation |
September 7th to 14th |
Granular placement |
September 15th to 17th South side |
Catch basin relocations |
September 23rd to 28th South side |
Concrete flatworks |
September 19th and 30th South side |
Pave cycle track |
October 1st to 6th South side |
Landscaping |
We hope to see you on the 27th.